/>

Adani allegations shine spotlight on India’s clean energy conundrum

The world’s third-largest emitter of greenhouse gases aims to raise clean power capacity to 500 GW by 2030.

Published : Nov 28, 2024 11:22 IST - 4 MINS READ

Coal accounted for 75 per cent of India’s power generation during the year to the end of March, with renewables such as solar and wind, but not including hydro-electricity, making up about 12 per cent. 

Coal accounted for 75 per cent of India’s power generation during the year to the end of March, with renewables such as solar and wind, but not including hydro-electricity, making up about 12 per cent.  | Photo Credit: JOTHI RAMALINGAM B

Bribery allegations against the Adani Group founder Gautam Adani have highlighted the growing problem India’s renewable energy developers face in finding buyers for the power they generate.

While India’s Central government wants to shift away from polluting coal-fired generation towards solar and wind, officials say state government-owned power distribution companies responsible for keeping the lights on have dragged their heels over striking renewable purchase deals. US authorities allege that Indian billionaire Adani conspired to devise a $265 million scheme to bribe Indian state government officials to secure solar power supply deals, after one of his companies was unable to secure buyers for a $6 billion project for several years.

The Adani Group has denied the charges.

The conglomerate is not alone in facing increasingly long delays in signing up buyers for the renewable electricity capacity, which is now being developed in coal-dependent India, the world’s third-largest emitter of greenhouse gases.

Also Read | COP29: How rich nations ducked their climate finance duties

Coal accounted for 75 per cent of India’s power generation during the year to the end of March, with renewables such as solar and wind, but not including hydro-electricity, making up about 12 per cent. India is still more than 10 per cent short of its much-publicised pledge to add 175 gigawatts (GW) of renewable power by 2022.

That has led the federal government to ramp up bidding for renewable projects to meet an ambitious 2030 target of increasing its non-fossil fuel capacity to 500 GW. In the five years to March 2028 it plans to tender for more than four-times the capacity of renewable energy projects it commissioned in the preceding five.

To push States to help meet India’s overall goal, New Delhi in 2022 introduced so-called renewable purchase obligations (RPOs), which mandate that States increase clean energy adoption so that the national share doubles to 43.3 per cent in March 2030.

Honouring these RPOs would require 20 of the 30 provinces monitored to more than double the share of green power in their electricity mix, a February report by government think-tank NITI Aayog showed.

The problem is that India’s States are unprepared for the rapid rise in renewable generating capacity, lack adequate transmission infrastructure and storage and would rather rely on fossil fuel for supply than risk “intermittent” renewables.

Also Read | End of a roll: The curious rise and fall of Adani stocks

The challenges were stark in the case of Adani Green, India’s largest renewable energy company, which took over three years to strike supply deals with buyers for the entire 8 GW of solar power capacity it won in a tender widely publicised as the country’s biggest.

Demand pool

Yet setting targets for tenders and issuing contracts is “meaningless” so long as interest from power distribution companies is so low, said R. Srikanth, energy industry adviser and dean at the National Institute of Advanced Studies.

And the allegations against Adani are likely to result in a further renewables slowdown, as low-cost finance from foreign investors may become more difficult to secure, Srikanth added.

A change in the way some tenders are run has exacerbated delays in the time it takes to complete renewables projects. The tender won by Adani Green was the first major contract issued by state-run Solar Energy Corp of India (SECI) without a state-guaranteed Power Purchase Agreement (PPA).

When announced in June 2019, SECI said buyers were guaranteed, but it withdrew the provision from the deal signed a year later.

SECI’s chairman told Reuters last month that a three-fold increase in tendering of renewable projects has left 30 GW of projects for which bidding is complete, but without buyers. Brokerage JM Financial said that it now takes eight to 10 months to sign power supply deals after a contract is awarded.

By comparison, companies that were awarded contracts between July 2018 and December 2020 needed around three months to strike supply deals, SECI data showed.

“Taking buyers into confidence before inviting bids may minimise delays in signing power supply agreements.”Rakesh NathFormer chairman of India’s Central Electricity Authority.

“The sudden surge in bids, large pipeline of projects under construction, mismatch in power demand and bid-pipeline, and constraints in timely execution of projects are leading to delays in signing,” JM Financial said.

One solution, said Rakesh Nath, former chairman of India’s Central Electricity Authority, would be knowing how much power buyers want before projects are bid for. “Taking buyers into confidence before inviting bids may minimise delays in signing power supply agreements,” he said. 

Meanwhile, International Holding Co’s (IHC) outlook on investments in India’s Adani Group remains unchanged, the Abu Dhabi conglomerate said, following the US indictment of Adani. “Our partnership with the Adani Group reflects our confidence in their contributions to the green energy and sustainability sectors,” IHC said in a statement on Wednesday.

Sign in to Unlock member-only benefits!
  • Bookmark stories to read later.
  • Comment on stories to start conversations.
  • Subscribe to our newsletters.
  • Get notified about discounts and offers to our products.
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide to our community guidelines for posting your comment